Delay Task- One worked, One Didn't

Options
Anna_272419
Anna_272419 Posts: 42
edited July 2020 in Questions

Hello,
I have a workflow which sends out emails at 8, 9, and 10 weeks after the process kicks off. I have the workflow calculate these dates at the beginning of the process, and then set the email steps to delay based on the appropriate field.

One of the steps did not delay correctly, and I received an email immediately after the workflow started. The next step (9 weeks) was delayed correctly:

I double-checked the dependencies and the delays and everything seems correct. What am I missing?

Thanks!

Best Answer

  • Anna_272419
    Anna_272419 Posts: 42
    Answer ✓
    Options

    Hi @Jozef_783863 , I double-checked my trigger and it turns out I changed the field reference name in the 8-week step, but did not update the delayed step. Mystery solved!

Answers