Is there a field that reflects which member of a group has completed a group assigned task?
Options
Dominik_704810
Posts: 7
in Questions
We are assigning tasks to a group, but for audit reasons, we need to reflect which member of this group actually completed this task. Is that possible?
0
Best Answer
-
you can use the global field tasks["task-name"].completedBy
6
Answers
-
A helpful note: If that task gets completed, re-opened, and completed again, the formula needs to be a bit more complex if you want to capture the most recent
completedBy
. See this thread: https://community.pushbot.com/discussion/635/recording-completedby-with-use-of-loops2